House #18

This page was updated on 29-Jan-2008

Please plan to join us at the dedication of this house, to be held at the house on 9 February.

House # 18 is completed! Thanks to all the great volunteers that have come out and helped to make this dream a reality!

Be sure to visit the Public Relations page of this website to see more pictures of volunteers at work!


Wrapping up odds & ends during the week
Kitchen completed

 

Dec 15th sealing heating ducts, shelves in closets, another coat on trim/doors
Sealing the heating ducts
Laundry closet

 

Dec 8th trimwork, replace a cabinet,
Painting more trim...
Replacing a cabinet
Installing striker plates

 

On December1st, much trim was installed, puttied & painted by a group of volunteers from Skidmore College.
Painting trim
House by 1 December

 

During the week of the 26th, kitchen cabinets were installed and trim prepared.
Cabinets in, trim prepped

 

On November 24th another coat of paint was applied to walls and ceilings. The cabinets and trim had been delivered. House electric had been connected.

 

On November17th, a coat of paint was put on all interior walls and ceilings, with a second coat in the kitchen area. Also the land had been graded.
Backyard
Roll, roll, roll
Peggy cuts in

 

On November 10th, the shed roof was completed, railings installed on outside stairways, a trench was dug for the propane delivery line
Trusty trenchers
Shingling the shed
Side landing railed

 

On November 3rd the sheetrocking was completed, taping was begun, the side steps modified and a shed built
Side landing lowered
Storage shed

 

October 27th much of the sheetrocking was completed.
almost ready for taping!
Kitchen ceiling
Bedroom wall

 

October 20th the siding was completed, electrical roughed-in, and much of the insulation was done. Porch railing was installed and the plumbing inspection completed.

 

On October 14th, more siding was completed
As of 13 September 2007
Also during the week, the septic system was completed...
May not be pretty, but necessary

 

More siding on October 6th, as well as porch railings and side stairs/landing
Board member Jason works on the siding
A unique perspective of the build!!

 

On September 29th much of the siding went up, and most of the front porch was completed.

 

The doors & windows went in on 22 September, and the bathroom plumbing was started
Front of house with volunteers
REar view with windows in
Sealing around the front window
There goes the tub!

 

Shingling the roof was done by a group of volunteers on 15 September
Completed roof!
Volunteers hard at work!
Almost there...
Not too steep

 

After the work party on 8 September, the roof trusses were up & much of the sheathing was completed!
Roof sheathing done...
Rear of the house
Watch where you step!
Frist truss lifted into place

 

After the second work party, the walls were completed. Special thanks to the young adults from Skidmore College who showed up to do a full day of nail pounding & wall lifting!
End of 2nd work day
View of walls...
Inside walls going up
Wall 2 is up!
Everybody lift!!
OK, on 3 we lift!
1st wall is up!

 

Ready for the volunteers on Saturday...
Floorplan layout

 

After the first work party, the floor was completed.
Floor is on foundation

 

Here is a picture of the site after the footings were poured & ready for the first work party
Sills on foundation & main support in place
Foundation poured

 

Here is a pic of the land after it was cleared...
In the beginning...

 

 

 